Time and Work Calculator

Treat each worker as a rate of work per day and combine them to find how long the job takes.

Time and Work Calculator

All fields are required unless marked “optional”.

Your result will appear hereFill in the fields and press “Calculate”.

Formula

  • Rate of a worker = 1 ÷ (days alone)
  • Together: days = 1 ÷ (1/a + 1/b + 1/c)
  • Other worker: 1/b = 1/t − 1/a
  • One whole job = 1

Add the work each person does in one day, then divide 1 by that sum.

Worked example

A in 10 days, B in 15 days

What do you want to find?
Days to finish together (2–3 workers)
Worker A alone (days)
10 days
Worker B alone (days)
15 days

Days to finish together

6 days

Combined work per day: 16.6667%

How it works

If A can finish a job in 10 days and B in 15, A does 1/10 of it per day and B does 1/15. Together they do 1/10 + 1/15 = 1/6 per day, so the whole job takes 6 days. Each worker's share of the finished job is in proportion to their daily rate.

The same rate method works for pipes filling a tank (a draining pipe has a negative rate) and for any shared task. If A starts alone and B joins later, the tool works out how much is left when B arrives and divides by the combined rate. For proportion-style problems with men and days use Proportion Calculator (inverse mode).

Assumptions and limits

  • Every worker is assumed to work at a constant rate and not get in each other's way.